FESCO New Connection Complete Procedure
Want a brand-new electricity connection from FESCO (Faisalabad Electric Supply Company) and don’t want to get lost in jargon? This guide walks you through the entire process—from eligibility and documents to applying online, paying the demand notice, installation, and realistic timelines—so you can get energized without the headaches. FESCO New Connection
Quick Answer:
To get a new FESCO connection, gather required documents (CNIC, ownership/tenancy proof/NOC, wiring test report, neighbor’s reference number, etc.), apply through the official ENC portal, submit and track your application online, receive and pay the Demand Notice, and coordinate for meter installation. Standard timelines follow NEPRA performance standards for new connections.
Understand the FESCO New Connection Ecosystem
FESCO is one of Pakistan’s ex-WAPDA distribution companies serving Faisalabad and adjoining regions. Like other DISCOs, it processes new service connections through a standardized path: FESCO New Connection
- Application (online via ENC or at the office)
- Document verification & feasibility
- Demand Notice (DN) issuance and payment
- Installation & meter energization
Most applicants today use the ENC—Electricity New Connection system. It’s the official, centralized portal for new connections across DISCOs, including FESCO, making it easier to apply and track from home. FESCO New Connection
LSI keywords to keep in mind:
FESCO new meter, FESCO connection charges, FESCO demand notice, FESCO ENC apply online, FESCO application tracking, FESCO wiring test report, NEPRA new connection time frame, FESCO new connection documents, FESCO domestic connection, commercial connection FESCO.FESCO New Connection
Eligibility & Connection Types

Who can apply?
- Property owners (residential, commercial, industrial, agricultural)
- Tenants, legal occupants, or society/association reps with proper authorization/NOC
- Developers for new projects and shops starting a business
The application form captures the connection category (domestic, commercial, industrial, agricultural, temporary, etc.) and the sanctioned load you’re requesting (kW). Choosing the right category and load keeps your tariff and safety in check. FESCO New Connection
Documents You’ll Need (Checklist)
Core documents (most cases)
- Applicant CNIC (front/back)
- Proof of ownership (registry, allotment/possession letter, mutation, etc.) or NOC from the owner if you’re a tenant/relative FESCO New Connection
- Neighbor’s reference number (from a nearby bill) to auto-map feeder/area in ENC
- Wiring Test Report (by a licensed electrical contractor/electric inspector, as required by category)
- Undertaking/affidavit (as per form—e.g., no illegal connection, dues clearance, etc.)
For commercial/industrial:
- NTN, company letterhead, incorporation/partnership docs
For agricultural:
- Land records
How to Apply via ENC (Online Application)
Step 1 — Go to the official portal
Select FESCO as your distribution company and provide the neighbor’s reference number to populate area details. FESCO New Connection
Step 2 — Fill in the application form
Provide:
- Applicant details: Name, CNIC, mobile, email
- Premises details: Exact installation address
- Connection category & load (in kW)
- Ownership status and NOC (if applicable)
Step 3 — Upload documents
Upload the scanned documents from your checklist.
Step 4 — Submit & note your tracking ID
Once submitted, you get a reference/tracking number. Save it and your registered mobile/email for subsequent status checks. FESCO New Connection
After Submission—What Happens
Feasibility & verification
FESCO verifies your documents, checks network capacity/feeder availability, and may schedule a site visit. FESCO New Connection
Demand Notice (DN)
If feasible, FESCO issues a Demand Notice (an estimate of connection charges—service line, meter cost, security deposit, etc.). Amounts vary by category, distance, and load. Pay the DN within the validity period.
Installation & energization
Post DN payment, the connection work is scheduled. Depending on the load/category and local conditions, a team installs the service line, meter, and seals; then energizes the supply.
Timelines—What’s Reasonable?
NEPRA establishes service standards for new connections. Practically, time is counted from application registration to connection provision, excluding delays beyond the company’s control (e.g., right-of-way issues, consumer-side readiness). FESCO New Connection
Real-Life Example
Ayesha, a teacher moving into a newly built 5-marla house near Jaranwala, needs a domestic single-phase connection.
- She collects her CNIC, the house registry, and requests a wiring test report from a licensed electrician.FESCO New Connection
- Her neighbor shares their bill, and she notes the reference number.
- On the FESCO ENC portal, she selects FESCO, enters the neighbor reference, and fills the form with a modest 3.5 kW load.FESCO New Connection
- She uploads documents and submits.
- A field team visits; feasibility is fine. She gets the Demand Notice, pays it promptly.
- Within the indicated time frame, her meter is installed and energized.
Common Pitfalls (and How to Avoid Them)
- Unclear ownership/NOC → Always use a proper NOC with CNICs.
- Missing wiring test report → Get it from a licensed contractor.
- Wrong category/load → Domestic vs commercial matters.
- DN payment delays → Pay promptly to avoid expiry.
- Address mismatches → Ensure consistency across documents.
Offline (Manual) Application—Still Possible?
Yes. You can still pick up forms from FESCO, fill them, attach documents, and submit at the relevant subdivision/circle office. But ENC remains the most convenient and traceable option.
How Much Does a New Connection Cost?
Costs depend on:
- Service line length/material
- Meter type (single/three-phase)
- Security deposit (based on sanctioned load and tariff)
- Special works (poles, transformer augmentation for high loads)
Always rely on your official Demand Notice.
Tracking & Communication
- Use your tracking ID on the ENC portal.
- Visit the office if there are pending queries or unusual delays.
Compliance & Consumer Rights
NEPRA Performance Standards outline obligations, including time frames for new connections and voltage quality. FESCO New Connection
If you face unusual delays:
- Confirm that all your documents are complete.
- Verify that DN is paid.
- Politely reference service standards when escalating.
Special Cases
- Temporary connections → For construction/events.
- Load enhancement → Apply for additional load if needed.
- Net metering → Separate process for solar setups.
Expert Tips to Get Approved Faster
- Keep CNIC, address, ownership proof consistent.
- Use a neighbor’s reference number.
- Hire a licensed electrician.
- Pay DN quickly.
- Track status online.
FAQ
Q: Can I apply without visiting a FESCO office?
Yes, through the ENC portal.
Q: Do I need a neighbor’s bill/reference number?
Yes, it helps with area mapping.
Q: How long will it take?
Depends on feasibility and category, but NEPRA standards guide timelines.
Q: What if my DN expires?
You must request reissuance.
Q: Do tenants need an NOC?
Yes, along with the owner’s proof.
Q: Can I choose single-phase or three-phase?
Depends on your load requirement.
Summary
- Apply online via ENC.
- Track application.
- Pay Demand Notice.
- Coordinate installation.
- Get supply energized.
Final Thoughts
Applying for a FESCO new connection is straightforward if you prepare documents correctly, use the ENC portal, pay the Demand Notice on time, and track progress. With careful preparation, you can avoid delays and enjoy a smooth connection process. FESCO New Connection